Central Coast Granny Flat – Week 5

 In Granny Flats Central Coast, News

Week five was a big week with the construction of the granny flat reaching lock up stage – always an exciting prospect for our clients! We are well ahead of our initial estimated timaeframe, even despite all the rain we’ve had. So this 12-week project is likely to come in ahead of schedule!

The tasks we undertook this week included:

  • completing the services rough in
  • plasterboard internal linings
  • waterproofing to the bathroom
  • insulation installed

Click here to review week four.